The San Bernardino County Public Works Department has completed the Baker Boulevard and Park Avenue project in the Baker Area. The project construction contract cost was $3,869,000 and was funded with Measure “I” Local Street Program – North Desert Subarea funds. The work, in general, consists of mill and overlay; sidewalk repair; and replacement of curb ramps with ADA compliant ramps; and traffic signal installation and doing other work appurtenant thereto. The project aligns with the County and the Chief Executive Officer’s goals and objectives of ensuring the development of a well-planned, balanced, and sustainable County by preserving and improving the structural integrity of existing road surfaces and providing Safety, Health and Social service needed for County Residents.
Before




After