The road improvements in the Chino and Montclair Area #4 started October 2022 and were completed in August 2023. The work consists of milling and overlaying with various resurfacing treatments…
84 results
Category: General
The road improvements in the Chino and Montclair Area #3 started March 2023 and were completed in May 2023. The work consists of milling and overlaying with various resurfacing treatments…
The work consists of milling and overlaying with various resurfacing treatments including rubberized hot mix asphalt, geotextile membrane, scrub seal, slurry seal, chip seal, leveling course, and striping. A few…
Following heavy rains on September 12, 2022, Oak Glen experienced significant mud and debris flows. In response, the Flood Control District (FCD) collaborated with the Natural Resources Conservation Service (NRCS)…
To enhance safety and effectively monitor potential flood risks, the Flood Control District (FCD) has installed 18 additional flood control cameras. These cameras have been positioned in key locations throughout…
The work consists of milling and overlaying with various resurfacing treatments including rubberized hot mix asphalt, geotextile membrane, scrub seal, slurry seal, chip seal, leveling course, and striping. A few…
The San Bernardino County Public Works Department has completed the Sand Canyon Road Project in the Redlands Area (Project). The Project was funded by Discretionary General Funding allocated for the…
Work consists of repainting roadway striping and pavement markings including School Zone advisory legends, speed limit legends, Stop Ahead / Stop / limit line legends, and cross walks in the…
All county offices will be closed on Monday June 19th in observance of Juneteenth.
Crews work in Trona area on shoulder erosion repairs. To date the area has had 4.73 inches of rain this season when yearly the average is about 2.30 inches. Crew…